The weather is all over the thermometer these
days and today was the coldest yet. We
had a meeting with our interior designer at the house so she could take a look
around. We discussed some design ideas,
but they were mostly put out there to get our minds working on the future. Our second meeting was with Geoff and Great
Oaks for the landscaping. He brought out
his pool design/installer subcontractor so we could talk about the logistics of
an ICF pool, which he has never built before.
Money will soon be pouring out of our pockets for all the preliminary
landscaping structures that need to be implemented to support the
driveway. We also got a chance to drop
of the revised landscaping plans to the HOA.
Not a ton of work has been done since the weekend
before. The week was a little wet, so it
probably slowed progress down. More prep
to the second floor was finished, but there still looks like some work needs to
be completed before the pour. We’re in
the third week of November now, so time is really getting short. A mid-December button up seems less likely.
The LiteDeck for the stairwell
going up has been cut to shape but forms still need to be added for the
concrete pour. Remember, the steel beam
next to the stairwell will be cut out after the pour so this will be open all
the way up. Should be a pretty dramatic
look. We discussed stairway railing and
baluster design with Margaret, but I think we’re still undecided on what we’re
going to go with.
Another shot of the
stairwell. This wall will go all the way
up to the ceiling and we’re also trying to figure out if we’re going to have
some kind of paneling or wainscoting traveling up the stairs. If we did, it might need to continue on the
second floor rotunda walls as well. It’s
a more traditional look, but if implemented cleanly, could look a little modern
as well.
Some of the “halo” is up on the
exterior wall. As with the first floor,
a single course of exterior wall ICF is added to act as a form for the floor
pour. This allows the floor to tie directly
in to the wall rebar spikes, which continue up into the second floor walls. Again, this floor will be a monolithic pour,
starting with the beam pockets, which contain helix steel fiber. When it’s still wet, but setting, the floor
will be poured without the helix fiber.
I hope I can get a pour date, and maybe take some time to watch the
process. Not enough movies of the build.
Detail of what the “halo” looks
like next to the LiteDeck flooring. You
can see the channel that will be filled with the pour, which actually fills
some of the top of the first floor walls.
The curved rebar pieces you see there are part of the ICF header above
every door and window opening. From this
angle, I think one more course of exterior wall ICF is required since the slab
will be about 3” above the LiteDeck.
Here’s what the second floor
looks like right now. You can see the
interior wall of the elevator shaft, which looks like it’s built up to the
correct height for the pour. Considering
another course of exterior ICF needs to be installed, and the turret still
needs to be completed, looks like there’s a good amount of prep required before
the pour. I’m guessing (hoping) they’ll
attempt a pour next week.
Parting shot of the rotunda from
the front door. Looks like a
post-apocalyptic war or something (playing too much Fallout 4). I think all the temporary supports are up so
at least everything is prepped from below.
As I’ve mentioned before, the
windows have been sitting in the warehouse since Spring but we should be able
to take delivery soon. Normally the bank pays out loan disbursements after
installation, but they said they would be able to approve a draw on the windows
if they get a clear receipt of delivery.
With the delay in the second floor, I’m not sure we should take delivery
before Christmas. I guess it depends on
how much shutdown will happen around the holidays.
We’re rolling forward on getting
landscaping approval from the city. They
required a right-of-way permit, which I called in to get extended until next
May. It’s required for improvements to
the driveway since we’re connecting with county roads. We’ll need to have all the silt fence and
orange barrier fence installed before the city will grant approval. We’ve decided to install the 600’ of orange
fence ourselves since we’ll want the freedom and flexibility to remove and
reinstall it as we progress through the landscaping phases over the next few
years. When we get the pool design
approved, we can start excavation and use that as fill dirt for the front
yard. A few retaining walls are required
so the timing of all these steps is delicate and all costs are out of pocket
since they’re not rolled into the mortgage.
No comments:
Post a Comment