Monday, February 13, 2017

Basement Stairs!

   A short thaw last week melted much of the snow at the site, but a longer freeze quickly turned the water into the ice that's coating most of the ground around the house.  The driveway in is a sheet of ice and if not for the ruts, would be difficult to traverse by car.  Fortunately, the daily traffic of work vehicles have melted enough ice to make passage possible which allowed our weekly visit to the house.
   Last week, we had a 5 hour marathon meeting with Margaret at Virginia Tile to finalize all the tile and counter top selections.  I'll make a separate blog post later this week to document our choices.
   This week saw more rough electrical installation, gas connections, rough plumbing testing, exterior stone, and most excitingly, the basement stair installation.  Rough inspections are scheduled for this Tuesday so after that, the house will be cleaned up and prepped for drywall installation.  The first floor stairs should be installed soon.

   Defying the cold, the stone masons at Old Country Stone (old-country-stone.com/) have been hard at work finishing the exterior stone siding around the great room but they also installed almost all the cinder block around the back deck to furr out the wall.  Last week they installed the angle iron used to support the block and this week saw the completion of the installation.  I'm not sure if they need to parge this before they attach the exterior stone or if the cinder block is enough prep surface.  I didn't take a close enough look, but I'm guessing the cinder block is tied to the ICF with straps of some kind that don't visibly protrude through the mortar joints.  The plumbers also roughed in a hose bib in that odd corner between the garage and porch.  I can't think of any other purpose to that space, save for a rain barrel.

   The cinder block continues around the gazebo, but stopped short at the fireplace location.  The fireplace slab was cleared of fill dirt so that OCS can begin to install the fireplace.  It will be a wood burning fireplace that we would like to integrate into seating and a barbecue area.  We submitted rough plans to OCS for refinement and price quoting.

   Here's a render I created and sent to OCS to give them an idea of what we're trying to accomplish.  We always envisioned that the raised fireplace hearth would be 18" high and seamlessly mesh into the perimeter benches.  The surface would then raise to counter top height at the corner, which would be where the barbecue would be.  I'll have to get opinions on the safety of having the barbecue under the roof; I'm not sure if there's enough gap to vent the heat or if the paint will be adversely affected.  I've also entertained the idea of a wok burner out there, but might save that option for a later date.  The counter top will probably be a dark granite of some kind, for easy cleaning and weather resistance.  As I said, it's a rough plan that I'm hoping OCS will be able to refine.

   The excavator removed the fill dirt at the outdoor storage door location and cleaned up the dirt from the footing so that OCS can start to install on that side.  They already installed the expanded metal lathe on the side, but not under the porch.  We'll need to remove the brick ledges in these locations to install the stone properly.  The grade at this point will be 2 feet up from the walkout grade, but the stone will still probably go down to the footing.  The hill on the left of the door, up to the gazebo, will be tiered with retaining walls.  Great Oaks will eventually install this wall and it will be made of the same caramel mint stone.  This will probably be the second to last landscaping implementation since we need to work from the backyard forward.  Until then, I hope to grass the hill to avoid soil erosion.

   OCS completed and de-tented the side of the house under the porch.  This portion of the wall is completely mortared and cleaned so this is the final look of the house.  They still have to install above the porch level and will probably complete this when the weather warms up a bit since it will be harder to tent.  I'm really loving the look of the stone and I'm glad we went with OCS.  The color selection and implementation is perfect.

   Here's the front corner of the house where the landscaping stones were removed from.  There's a bit of parging up at the top near the beam, but I don't think they plan on installing below grade at the landscaping wall.  The corner is completed and that's all that's really needed.  I'm also not sure how much will be completed under the deck on the front of the house.  The grade does fall away a little towards the retaining wall and the exterior wall will be visible from the lower elevation so I'm thinking that they'll finish the entire space.

   Here's what still under the tent.  The side of the great room looks completed with filled mortar joints and installed stone ledge, but the back still sports unfilled joints.  With warmer weather coming this week, and water installed in the house, I'm sure they'll make quick work of this section.  Future landscaping will see the installation of a paver patio under the deck in this area.  It extends around the corner to the said basement walkout and offers yet another nice place to convalesce.  We're considering if we need some kind of water diversion system in the deck above, to keep this area dry.

   Here's a closer look at the installation of the stone sill below the window.  It's made up of two sections of limestone and fits perfectly in the space left by the stone installation.  The surface is honed and feels slightly rough, which is perfect for this setting.  There's currently an extension cord coming through the partially opened window if you're wondering what the cable is.  While there's a live electrical receptacle on each floor on the interior, none of the exterior sockets are live.

   Here's a pallet of limestone sill sections ready to be installed.  I'm not sure if these are going to be used under all the windows, or if there are longer sections for the first floor stone ledges.  They're fairly heavy and being made of stone, not prone to break free flexing, so it might be possible that these short sections will be used for the majority of the house.

   There's a pallet of corner pieces in the garage waiting for installation.  It's amazing to think that these were once small boulders that were cut on two sides.  I'm sure there will be more needed than these for the entire house but this seems like it's enough for most of the house.  They won't be needed on the gazebo since it's a larger angle than 90 degrees.  It will be used on the back porch, around the garage, and on the front of the house above the porch.

   Here's what's completed on the back of the great room basement level.  This is the walk out for the exercise room and it's mostly completed.  I think all that's left is to fill the mortar joints and add the stone ledge under the windows.  I don't see any flashing installed above the windows so I'm guessing that the mortar and window flashing is enough to waterproof the exterior.  There will eventually be another stone patio at the walkout, but not as extensive as the side walk out.  All these patios will be connected with a blue stone path, which will in turn lead to the outdoor storage and back yard.

   The carpenter is still hard at work cutting and installing the arches.  He's there everyday whittling down his to-do list and these arches are pretty demanding.  The spaces between the posts aren't consistent around the porch, but to keep the look of the arches consistent, the ratio of arch to post needs to be similar.  A lot of calculation is required to pull this off.

      The arches are installed on both the back and front of the beams and will look like they sit on the top of the post once the post sleeves are constructed.  We're having some trouble figuring out how these arches will extend around the round portion of the porch, so Mike is bringing in an architect to get some ideas on how to complete the look, ensure structural integrity, and provide a good final product.

   On to the inside, the stairs to the second floor were temporarily removed so the electrical installers could finish the rotunda lights.  We're hanging a large chandelier from the center of the rotunda, so an electrical box was required.  The installers weren't comfortable with spanning the rotunda with platforms so the temporary stairs were removed so they could use a tall ladder to install the rough box.  I'm not sure if they removed the stairs so the stair installers could get the basement stairs in since I didn't get to watch the procedure.  The temporary stairs were reinstalled a few days later so the inspectors could regain access to the second floor without climbing a ladder.

    The biggest addition this week, in terms of size and cost, was the curved stairs to the basement.  The stairs were constructed in their workshop and installed as one pieces.  I'm not sure if they went through the basement or front door, but the thing has to weight a ton and I can't imagine how they did it.
   The stairs are a consistent width up the stairwell but since it's a section of a large spiral, they're curved in two planes.  The treads are solid oak and the risers are oak plywood.  If I recall correctly, we'll have the treads stained to match the floors and the risers painted white.  There's something very liberating about walking up and down stairs in your own house for the first time.

   The sides of the stairs are constructed from veneered bent and twisted laminated beams.  I don't know if they formed up the laminations in the shop or purchased a laminated beam and bent it to match the curve radius, but if I had to guess, I would guess the former.  I don't know a lot about stair construction, but I've seen pictures of curved stairs being made in a shop, and they make a template that mimics the walls and construct the stairs within the template.  It's entirely possible they built up the laminations in the template then filled the treads and risers when those were completed.

   The treads are protected by a sheet of polyethylene sandwiched under a quarter inch lauan sheet so construction traffic won't mar the final wood.  The lauan is stapled to the tread so before the tread is stained and finished, it will probably be lightly resurfaced.  Each lauan piece is cut to the same dimension as the tread so the full coverage ensures that no damage will come to the stairs.

   Here's the underside of the stairs, to highlight the construction technique.  A plywood support block is nailed and glued to the inside of the laminated stringers and a wedge is installed on top of that to ensure the tread is level.  A vertical wedge is installed to ensure the riser is plumb since the support block can be installed off-square.  Blocks are installed where the front of the tread and riser meets to secure the two together.  It looks like glue is used between every joint to help prevent squeaking but after time, some adjustment might be necessary.

   This view won't be available when the basement is completed, but I'm not sure if drywall will be installed on the studs before move in or if it's up to us to get it done during the basement finishing.  The stair stringers form a double helix as they go up the stair well and it's a shame that shape will be hidden.  We'll get a little under-stair storage, but we're not sure what we'll use it for yet since we have a whole area devoted to basement storage.  It's curved, so nothing particularly long can fit in there.  Maybe I'll just make some curved shelves to line one of the walls.

   Another view that won't be possible once the first floor stairs are installed.  This is a shot down from the top of the rotunda.  The supports were there for a piece of plywood and are generally not needed anymore, so I'm not sure when they'll take them away.  Yes I bumped my head on it.  There will be fewer first floor stairs since they only have to ascend 9 feet plus the thickness of the floor, rather than the 10 ft plus thickness, for the basement.  The design of the first floor stairs will also be different.  The first floor will have an open stringer on the inside of the rotunda rather than a solid stringer.  Of course, there will also be a railing and balusters that will connect to the railing around the inside of the rotunda on the second floor.  As with the treads, the railing will be stained to match the floor color.
   One more shot of the under-stair storage in the basement.  I've seen some creative storage solutions for the space under stairs, but since the steel stud walls are structural, we can't cut in doors or drawers to the sides.  Any solution will need to be from this opening, which is made to support a door.  The distance to the designated basement storage room and this space is basically the same, so it doesn't offer any distance advantage.

   The outlet floor penetration for the kitchen make up air has been cut, but the ducting hasn't been completely installed yet.  This will sit under the base cabinet for the cook top and provide passive air make up when the kitchen vent hood is turned on high settings.  The gas for the cook top was also installed, through some trouble.  The gas pipe installer verified the pipe path with Mike, but decided to change the install, which took the pipe path through the middle of the theater room ceiling.  We've been working hard to keep the ceiling clear of mechanicals so we could maximize the height in the room.  I spoke to the installer about moving it, and he was super reluctant to do it.  It would have involved cutting and re-threading the pipe, which he didn't want to do.  A quick note to Mike set him on the installer to do it right and the installer acquiesced.  Nothing like having a bulldog in your corner.

   The supply of the make up air duct has been installed in the basement wall, but again, the duct run itself hasn't been installed.  Unfortunately the duct will have to go under the beam, but we'll find a creative way to box in the entire beam and hide the duct.  At least there's a good chance it won't impinge upon the basement ceiling.

   Porter and Heckman were busy completing the HVAC installation in the basement to the first floor since the second floor is complete.  Part of this is to install the ERV, pictured here.  What this does is provide fresh air to the house while recapturing the energy in the exhausted air.  It's an energy exchanger between the conditioned and exhausted interior air, and the unconditioned fresh exterior air.  It looks like some kind of industrial unit and as cool as it looks, I'm glad it's hidden in the mechanical room.


   One of the big questions remaining was how the second floor would be zoned separately from the first floor.  Since the first floor uses the in-duct inflating bladders, there was questions as to how the second floor would work.  Here's the answer to that question.  It looks like P&H installed a solenoid actuated baffle in the supply trunk that goes up to the second floor.  The solenoid will receive signals from the heater supply controller and open when the second floor thermostat requests heat.  Since the blower is variable speed, I don't think we'll need a bypass duct.  In systems with a single stage blower, a duct is needed from the main supply to the return so that extra air velocity can be blown off somewhere when the second zone baffle is closed.  In our system, when multiple thermostats call for service, the blower can increase in output velocity to supply more open ducts.  There should be some kind of indicator on the duct to show how open the baffles are, so I'll keep my eye out for it in the future.

   An impressive number of supply ducts have been installed that supply the first floor and basement.  All joints are sealed with mastic, which is code now.  When installation is complete, a blower door test will be performed to evaluate the amount of leakage in the system.

   Here's a shot of the current state of the mechanical room.  Eventually, the temporary furnace will be removed, opening the center of the room, but we still need to place and install the desuperheater, water heater, and A/V/D equipment.  Even still, the room is filling up fast.

   Porter and Heckman has nearly completed connecting all the basement ducts through the floor penetrations on the first floor.  There are many places where the air will be supplied through the toe kick of a base cabinet, and in these places, appropriately bent ducts are installed.  In cheaper installations, these will often be open to the base cabinet and the installers will simply use the base cabinet cavity as a heating chase, cutting a vent in the toe kick.  I'm not sure if it's code, but it's a pretty bad way to route condition air since some of it will be lost to the cabinet space.  This duct will be extended to the toe kick vent when the base cabinets are installed so all the condition air will reach the room.

   Here's the sticker for the rough HVAC inspection approval, performed on 1/26/17.  I must have missed it in previous visits.  HVAC rough inspection is one of the easiest since the inspector is just looking for floor penetrations and return openings, not final duct installation.  The rest of the inspections are coming this week and Mike says that the drywallers are on standby for installation so we should be closing up walls soon.

   The gas pipe has also been installed to supply the two fireplaces, as well as the dryer on the second floor.  This installation is clean and falls within one of the cavities left after the temporary support was removed.  Besides the gas supply to the back porch barbecue, I think all the gas has been installed in the house.

   Here's where the gas pipe comes up and branches off for the first floor fireplace.  I found the spec for our fireplace sitting in the area, so installation location was performed with the final product in mind.
   Here's where the gas pipe terminates at the second floor fireplace location.  Again, there was a fireplace spec here, so I'm not worried about installation.  Both fireplaces will have a blower to help circulate the heat. I'm hoping that with all the steps we're taking for insulation and air penetration efficiency, we would be able to heat the entire house with these fireplaces.

   Initially, the gas installer encountered some problems running the gas line for the second floor laundry room.  The wall between the laundry room is situated right on a beam so a direct penetration couldn't be done.  The water lines run in the garage storage space and in the first floor ceiling to reach the necessary locations on the second floor.  Mike used the mechanical chase created in the garage storage to route the gas line up to the second floor without any issue.

   Here's where the gas pipe comes up into the second floor and to it's final location.  The mechanical chase below is matched above where the master closet meets the laundry room.  Although it wasn't initially planned as a mechanical chase, it worked out well.  Word of advice for those in the planning stages, look for cavities to run mechanicals in.  It will make your life easier.

   All of the basement drain plumbing has been attached to the sewer system.  I found this particularly interesting looking.  It's the plumbing stack for the first floor guest bathroom.  There's an unconnected vent pipe in the ceiling in place for the future basement bathroom.  I was confused at it's purpose at first, when I saw the capped off PVC pipe, but then realized what it did when I traced it up to the attic.

   Here's the single roof penetration for the drain vents.  They disconnected it and put on a temporary cap and pressure gauge.  I guess both the supply and drains are pressure tested for leaks so the connection to the grinder pump must be closed off some how.

   This is the result of Mike negotiating with Porter & Heckman about the sufficiency of the supply in the turret room.  Mike was concerned with the number of windows in the turret creating a cold draft during the winter and suggested another supply duct be installed.  The two ducts that supply the room were initially placed in the ceiling.  During the design phase, P&H ran a schedule J to determine air supply load so they insisted the two ducts would be sufficient.  The compromise was to move the two ducts to the turret itself so that any cold air from the windows will be tempered with heated air.  This will work well since the air return is on the other side of the room.  This also works well to hide the air supply vents.

   The electricians were also hard at work trying to complete all the installations around the house.  I still haven't seen the cable run from the car EV panel to the garage, but this high gauge wire was run to the kitchen for the double electric stoves.  We also requested a 220V at the stove top location just in case we want to switch to electric induction in the future, which has yet to be installed.  Not much more left to complete before inspection this Thursday.

   The county finally got out to turn on the water and they painted the valve the standard blue.  There's one spigot currently installed in the basement and it is functioning so our house officially has water!  Just in time for the drywall installers.  Mike also finally got a sign up at the street.  Too bad we're kind of isolated from the main traffic because he deserves more exposure.

   That's about it for this week.  Next week should see the completion of all rough inspections and maybe a drywall delivery, but that might be premature.  The weather should be a bit more mild this week so we'll probably see progress on the exterior stone.  I'm not sure when the second set of stairs will be completed and delivered, but I'm excited to see them go in.  The porch storage access door will be cut on Thursday so we'll finally get to see what's in that tomb.  Next weekend should see some pretty exciting developments.





Monday, February 6, 2017

It's all rough in the basement now

   Winter is still in full force here but it's still not stopping our build progress both inside and out.  With HVAC rough inspection passed, the plumbing is currently being pressure tested and the rough electrical is nearing completion in the basement.  Gas pipe is being installed to the cook top in the kitchen, gas fireplaces, and clothes dryer in the laundry room.  On the outside, the carpenter is working on the arch fascias on the porch beams and the stone masons have tented in the side of the house and to keep working on the cobblestone siding.

   The carpenter boxed in porch beams in the round section under the turret.   Figuring this out was always a pain in the butt, but I think that given the non-equal spacing of the posts, Mike figured out a good way to normalize the distances in the header.  They buffed out the beam on shallow areas to normalize the distance to the porch roof fascia and covered it with cedar plywood, which will be painted to match all the trim.

   The electrician finished the rough install for the garage exterior lighting and most of the garage electrical receptacles.  They still need to run the large gauge wire for the 100A circuit that will supply power to the dedicated car charger and NEMA 14-50 socket next to it.  The exterior garage light boxes were installed in the bracket mount about 11" down from the bracket to allow for the shepherds hook style carriage light that will be flanking the garage doors.

   The masons tented under the entire side porch to create a warm space for installing the cobblestone siding.  They have two large bullet heaters inside to keep the space warm enough to work in and prevent the mortar from freezing during the drying/curing process.  There's a little gap to get inside near the rear basement walkout, but we went down the ladder into the basement to gain access to the workspace.  The top of the deck is covered in plywood so the heat retention is pretty good in there.

   Although the tenting stops at the porch deck on the side of the house, on the great room, they tented all the way up to the stone ledge so this will be the first part of the house to have the full exterior cladding applied.  I can't wait to see this completed because I think it's the most striking feature of the house; a three story facing with tons of windows.  The tenting material is some kind of fiber reinforced polyethylene sheet and seems more durable than a standard tarp.  It's transparent enough to let daylight in so they don't need supplemental lighting in there.

   Under the tent, progress is moving quickly.  This is the back of the house at the rear basement walkout.  The electricians have installed and wired sconce locations on each of the sliding doors as well as exterior electrical receptacles.  It's good they got them installed because the masons have to work around these penetrations.   They'll work this wall all the way up to where the stone ledge will be installed, and down below grade to the footing.  The gap below the window is for a stone ledge sill that will be installed when the rest of the stone ledge is installed.    

   Here's the inside corner between the side of the workout room under the great room and the rest of the basement. They had just started this area last weekend, so this, in addition to other parts, is the progress of a week.  I confirmed that the box base of the post will be scored to the exterior house wall and later be clad in cobble stone.  It looks like they're working in different areas of the wall so there's either multiple people working on putting up the stone, or they're picking and choosing which pieces of stone to put where.  There are some smaller pieces of chipped stone to fill smaller gaps.  At first, they look jagged and out of place, but once the mortar joints are filled, they blend right into the rest of the stone field.

   Here's the side walk out, showing how low below grade they install the stone; all the way down to the footing.  This stone will be covered up by landscaping, or in this case, a stone patio, but it's nice to know they take it all the way down. I don't know if there's a technical reason for it, or if it's just aesthetic, but it's a nice touch either way.  It looks like stone was placed under the sliding door, and was removed for some reason.  I don't think there will be a stone sill here too.

  There's a large section of the side wall that is completely finished, including mortar joints and joint finishing.  The mortar joints really flatten out the wall and helps to further secure the stones to the wall.  The surface of the mortar has a sanded finish, so I think they use a stiff bristle brush to smooth out the joints.  It looks fantastic when finished.

   Here's the corner of the house where Great Oaks pulled the stones away from to correct the slight cant in the wall, and so the masons could get the corner stones on the house.  There's a little bit of wire mesh at the grade, but no parging yet, so I'm not sure how far over they'll take the stone.  The landscaping stone will sit flush against this corner, and I'm guessing will need to be reshaped to back in.  Mike talked about trying to get some waterproofing material on this wall, but that would require digging out the location by hand.  I would appreciate the installation, but considering the labor involved, I could understand skipping it.  You can see the condition of the double thick polyethylene sheeting the previous crew installed, insisting it was sufficient.  Doesn't look like it held up even after only two years.

   Here's another straight on shot of the finished wall section.  Much of the dust has been cleared away from the stone so we can get a better representation of what the finished wall will look like.  It won't be sealed and I don't know sealing it is even an option so the color will never be wet vibrant.  I looks like it's mostly tan, blue, and gray with some slight reds mixed in.  I think it will be a good match to the rest of the house.

   Here's a close look at the difference between the mortared stones and un-mortared.  It looks like there's either some squeeze out of the back buttered mortar or they come through and add some mortar to lock the stone one before the joints are filled.  There's also a color and textural difference between the joint mortar and the stone adhesion mortar.  I'm guessing there's a bigger sand percentage in the joint mortar since the adhesion mortar is much smoother.

   Some tools of the trade.  These are the big pastry bags they use to squeeze the finishing mortar into the stone joints.  I didn't see any finishing brushes around, but there has to be some kind of tool to smooth out the joints after the mortar is squeezed in.  Since our water hasn't been turned on yet, the masons have been bringing their own water but we should be getting water service turned on this week.

   Since the wrong information was provided to the electricians before Mike came on the job, the electrical meter boxes were spaced for a brick installation instead of a stone.  Here's the elegant solution Mike came up with to provide a good mounting point for the meter boxes while preserving the spacing.  They'll be painted, but I haven't decided if we'll paint them white to match the trim of the house, or gray to match the mortar and electrical boxes.  They're constructed of rough-sawn cedar so they'll take paint well and should last forever considering they're very sheltered from the elements.  They provide a nice line for the stones to be installed against.  Also, all the exterior construction electrical receptacles have been removed and moved inside.  No more running extension cords up through the window!

Here's where the power enters the house.  The copper line is a grounding wire that's hooked up to the house circuits through the breaker box.  This is often tied into the main water pipe coming into the house since that goes underground, but since ours is a nonconducting pipe, that's not possible.  This just grounds into the ground with a large conduction spike.  This hole will probably be filled with a flexible insulating material.

   Here's a closer look at the gap left for the stone sill.  The red line denotes the border between the stone and sill.  I'm not sure how they'll mortar the gaps without the sill in place, so maybe it will be installed sooner rather than later.  This was a detail that I didn't think about, but obviously someone was.  The stone might have been able to go right up to the bottom of the window, but the sill is a nice finishing touch.  It will also help prevent water infiltration behind the stone when it's caulked to the window.

   Here's where the penetration for the make up air will be.  Because our kitchen exhaust fan ejects so much air, and the house is so tight, by code, we need to have a same diameter pipe to allow in fresh air to prevent combustion back draft from other appliances.  The duct will be 10" in diameter and be run through the kitchen floor under the base cabinet where the cooktop resides.  There will be an electronic damper installed inline that will open when the fan is set above a certain CFM.  We're still working out the details of electric heat to temper the air, and a filter box to filter out fine particles.

   All the angle iron has been installed on the back porch to accept the cinder block in preparation for the granite cobble installation.  This is a huge cost addition that could have been prevented by proper planning or better communication.  Of course, Mike picked up the issue and dealt with it best he could but I wish he had been around when this was built years ago so we would't have this trouble.   In the end, the fix will be invisible and the final product will be much better off because of it.

  The carpenter is working hard to install all the arched porch beam fascias and has completed much of the side of the house.  Unfortunately, the spacing of the posts isn't the same all around the porch, so there are a few different lengths he needs to make, thus the creation of this jig in the basement.  These arches will also be installed on the outside of the beam.  It's a little detail that adds a lot of character to the house.

   Inside, the plumbers have prepped the supply and drain systems for rough inspection.  A shower pan was installed in the shower locations so the drains could be leak tested.  Water will fill the pan to test the integrity of the fittings and ensure no leaks through the floor.  I don't know if the tubs will need to be tested as well, but the master shower will needed to be tested when more of it is installed.  It's such a large space that the inspector is allowing us to proceed before a waterproof test, and he'll revisit it when there's more installed.

   In the basement, the water supply system has been sealed at all the junction drops and pressurized to test the integrity.  The fittings here are temporary and only meant to test the system on the first and second floor.  The system is pressurized higher than operating pressure and the gauge is monitored.  If there's any pressure loss, then there's a leak in the system somewhere that needs to be fixed.

   The Sound Vision is completing their work in the basement and have also installed these two speakers in the kitchen so we can gauge the alignment with all the other light fixtures in the room.  I don't know what I was expecting, but it wasn't something that looks like this.  The entire unit fits up in the ceiling cavity and is completely contained and sealed.  There are two units in the kitchen that will provide sound to it and the eating area near by.

   I think the units are James Loudspeaker 63SA-7HO with an opening of 3".  They each have a 3/4 tweeter, 2" mid range speaker, and a 6.5" sub woofer with a recommended amplifier range of 25W-125W.  All of Jonathon's hardware selections have been perfect so I have full confidence these will provide more than what we need for sound.

   The boxes have been installed for power and data to the TV in the great room.  There will be a lowering TV mount so we can swivel the TV down to a more comfortable watching height when we want to, but I'm not sure what the wall behind the TV will look like.  We're applying a stone to the fireplace so I'm not sure if it will just be a drywalled area behind the TV or if the mount will be furred out to clear the stone.  I think the latter would be a more elegant solution but it might be one of those things that we still need to work out when the time comes.

  The Sound Vision also installed the lighting control panels in the basement and laundry room.  Here's the basement installation.  It's much bigger than I thought it would be but it has to house one controller for each circuit we want controlled.  I think the cut out will allow us to see the status of the controller without opening the cabinet.  I can see my self hanging out down here just to watch the blinking lights.  It will be amazing to see what this room looks like when the water manifolds and geothermal equipment is installed.  I wouldn't mind drywalling this room one day and the boxes allow enough space for a flush installation.

   Here's the laundry room lighting control panel.  It's the same size as the one in the basement but this one will be situated behind hanging drying racks.  The front panel screws to the box so there's no concern about an access door impinging upon any drying rods we have installed here.  The box will be flush mounted to the drywall and mostly sit in the 2x4 wall cavity.  It's a good thing we have the 2x6 wall in build out in the master bathroom otherwise we would have water pipe routing issues here.

   The electricians have installed all three electrical panels in the basement.  From left to right they're used for EV car charging, Geothermal, and house.  There are three breakers currently installed in the house panel, which supply a few receptacles around the house.  You can see the socket adjacent to the panel is hot and in use for the installers in the basement.  You can also see the common ground wire linking all the panels together.

   Here's a close up of the first powered socket in the house!  I'll have to double check to see if there's one near the sump pump area since that should be on its own circuit.  Speaking of which, we also need to figure out where the pump will eject and make the appropriate wall penetrations for that.

   Here's where one of the mechanical chases will be installed when we complete the basement.  Unfortunately, it's flanked wide by the HVAC trunks, but it does allow ample space for the AV/data lines on the left, gas pipe down the middle, and electrical on the right.  It's a clean enough installation and I hope that level of organization will continue when they go into the breaker boxes.  Most of the time the installers just bundle the cables together in a thick mass and that's acceptable.  It does offer an insight into the level of craftsman ship and personal pride so we'll see what happens here.  Not to nit pick too much, but notice how the A/V/Data lines installed by The Sound Design are placed up in the nailers while the electrical is all below.  Granted, there's much more work with installing all the electrical lines up there, but it does make a difference.

   Here's a closer look at the electrical runs.  There's no code citing how many NM lines can be contained by one staple, but there are usually manufacture suggestions on the staples themselves, which is usually two or less.  It looks like the installers are adhering to manufactures suggestions and installing a maximum of two per staple so I'm happy.

   Here's a closer look at the data side.  Each bundle goes through a nailer and the corresponding foam is cut away.  Nice installation.  The orange line is actually an electrical supply for the elevator equipment.  White is 14 AWG, yellow is 12 AWG, and orange is 10 AWG.  There also still needs to be a black 5 or 6 AWG for the charger in the garage that has yet to be installed.

   The orange wire runs a clean path around the elevator shaft to where we plan on putting the equipment.  The yellow line is a data line for the required hard phone line connected to the elevator.  I think the white 14 AWG line is there for electrical code.  We're still undecided on if we're going to install the elevator before c.o.p. but we're heavily leaning towards it.

   Porter and Heckman have also been pretty busy down here, connecting HVAC duct lines to floor penetrations.  Here's how the workout room will be heated and you can also see the ducts going to the great room.  All the supply ducts have the expansion damper installed so when all the ducts are installed, all those lines will have to be connected to a controller somewhere.  That's how the basement and first floor zones are being controlled.  I haven't seen any bladder dampers installed in the second floor ducts yet, so it's still a little mystery how those will be zoned off.  Lights have also been installed in this room.  It wasn't in the original plan, but we'll probably need to cover all the foam with drywall for fire hazard code, so we're installing as much as we can right now.

  Electrical receptacles have been installed and wired in the future theater, to code.  This is a long term project with no start date yet since we want to get all the landscaping installed first.  We'll probably bring The Sound Design back in to perform the equipment install so they've submitted a budget proposal for wiring the basement for A/V/D distribution.  I'm not sure who will perform the actual theater installation.


   The water meter has been installed and terminated but as I said before, the water hasn't been turned on at the street.  Mike says that should happen this week and we'll have a temporary spigot somewhere so the masons and drywallers have a water source to use.  I'm not sure when it will be connected to the rest of the house since we still have to install actual valve bodies and finishing trim kits.  Water should have been one of the first things installed in the house, but it was another one of those things that flew under the radar with the previous builder and his crew.

   This is the lowest the water meter will ever read.  It's funny that even though the water isn't on, the meter has turned a little bit.  Probably for some kind of factory test or something.  These meters usually have some kind of exterior data port connected to them so that's another wall penetration needed somewhere.

   Throughout the house, nailing plates have been installed on studs to protect the water lines from accidental puncture.  These are 10 gauge steel plates that will sit behind the drywall so if someone is looking for a stud to nail or screw into, they won't easily be able to penetrate the water line.  I've seen thinner plates used, so it's nice to have such a thick gauge plate protecting my lines.  These are probably needed to pass rough inspection.

   While we were visiting the house, the gas pipe installer was hard at work in the basement and the excavator showed up to remove the fill sand in the under deck storage location.  Mike wants this area cleared so we can cut open the ICF and access the area under the back deck to run the gas pipe to the barbecue area.  We'll also need to get a door installed in the newly cut doorway.  We haven't seen the inside of this in over a year, so it will be fun to see what was left in there.  At least there's nice pea gravel on the inside.

   Here's the gas penetration in the kitchen for the cook top.  They still need to run to the two gas fireplaces and figure out how to run up to the laundry room for the clothes dryer.  Of course there's an issue with the laundry room location.  The wall between the master closet and laundry room happens to sit right on a concrete beam so we can penetrate right up through the floor.  The plumbing installers came up in the side wall and ran through the wall to get to the washer location.  I think that area is too full to run the gas, but Mike is working it out so I'm not worried.

   So that's it for this week.  We have a meeting with Margaret this week to revisit tile selection and try to go over our lighting selections.  We still need to figure out much of the pluming trims in all the secondary bathrooms and haven't even touched door hardware yet.  Besides paint color selection, those are the last big decision to make.  Hopefully we'll get the electrical inspection passed and we can start drywalling!