Monday, September 9, 2024

All Plumbed Up

   Progress continues with the plumbing of the filtration equipment, light installation, and rough in for gas and electric supply to the equipment pad.  Inspection for the underground pipes is tomorrow, after which the trenches will be filled.  Eli says his crew should be done by Wednesday and plaster will be early next week with water coming soon after.  We're racing to the end as the check list grows shorter.

   The sun deck bubbler saw the addition of this translucent collar and the RGB led light.  The water flows around the light and there's an additional clear cap and water diffuser that will attach to the top of this.  There's an optional snorkel and eyeball if you want that look and a winterization cap that I might have to pick up.
   Here's what the lights look like installed.  They're all RGB lights so we can make lots of different colors in the pool.  I'm not sure if the software cycles colors or if you have to manually change the color of the lights and they remain static otherwise.  Even if the native software doesn't cycle colors, I'm sure I could write an automation to have the colors change periodically.  I wonder if I could find an integratable chlorine probe and have the lights display colors based on the value.
   All the lights and return jet flanges have been installed.  The grass side wall has two lights and one water return.  I think this return is plumbed together with the jet in the deep end.
   Here's the return in the deep end with the deep end light.  When I winterize the pool, all the return jets will be on at the same time since they're all on a single ball valve.  If the blower is strong enough, I can get all the returns to push air and cap them off one by one.  If it's not, I'll have to cap them and uncap them in pairs (grass and lake) to make sure the primary runs are blown out.
   Here are the lake side returns.  There will be pool return jets that screw into the return ports, but I haven't seen what they look like yet.  Often they're aimable balls, but we'll be rotating the water counter clockwise around the pool.  During the winter time, you don't need to drain the water below the return jet level, but you do need to use a blower to evacuate water in the lines and plug the jets to prevent water from flowing back in.
  Here's the gas and electrical conduit supply coming from the house.  They're not currently connected but inspection is required on the run before it's covered over with dirt.  The water pipes have been covered but the electrical conduits remain visible for inspection.
   The rats nest of black wires is all the LED lights before they're wired into the automation panel. The panel box is sitting wrapped in the black garbage bag so I haven't gotten my eyes on the actual hardware but everything I've found on the part number shows that it has an air and water temperature sensor.  The water temperature sensor is self explanatory, but the air temperature sensor can be used for freeze warning conditions.  Anything that can be automated will be provided by this unit, so hopefully Jandy isn't stingy with their output information and software APIs.
   Here's what the pad looks like after the plumbing has been installed.  All the unions where the supply and return pipes are connected are unfortunately buried under the ground and I didn't get to look at them.  If I did want to connect a valve to each of the returns, still grouped in 2s, I would have to dig them up and hopefully have enough line to add the appropriate connections.  Not the worst job, but not super fun either.  They left enough hard PVC to make repairs or new connections so I won't have to replace everything.
Here are the filtration components after the filter canister and water heater.  The clear thing in the T coupling is the additional sacrificial anode.  Next is the copper water sanitizer.  Those go into the heater which has it's own sacrificial anode, which was moved to the front input.  The 90 degree sweeps that Jandy supplies have a half inch plug for something, but I'm not sure what they're for yet.  From the output of the heater, we have a check valve to prevent water backflowing from the supplies.  Since the whole equipment pad is lower than the pool, if we don't have a check valve on the returns, water could backflow through the returns, back into the filtration system.  Lastly, is the salt water chlorinator.  Although the way it's installed isn't in the recommended configuration in the manual, Eli says it's okay.  The manual does allow those ports to be used, but suggests it to be in the vertical position.  The sensor will be in the end port, which is supposed to be the serviceable component.
   Here are the two supply pipes coming into the pump.  One is a combined skimmer input and the other is the main drain.  Hopefully there won't be a problem with how the two skimmers are plumbed in.  Going from two, 2" pipes into one 2" pipe, which is further combined with the 2" pipe from the main drain is a pretty drastic flow reduction but I'm probably over thinking things.  As long as the pump isn't being starved for water, it should be just fine.  One thing that I requested to be added is a T on the pump input, that will be capped off.  It will allow me to connect a blower to the system for winterization.  Other people have drilled the clear pump cap to attach a cyclone blower to blow out the system, but I would rather have a junction in there.
   Lastly is the return side of things.  All of the returns are fed from the right side of the manifold.  The power actuated valve on the left is for the bubbler and allows remote control of the bubbler water flow.  The valve for the water jet returns has a 2" to 1.5" union so again, I'm hoping the flow isn't choked too much with this reduction, then further reduced when it splits two more times down stream.  I have experience calculating hydrodynamic flow rates in pipes from my marine aquarium days, but from what I've read online, pool designers don't really care about matching cross-sectional flows of the plumbing.
   Thanks it for now.  Inspection is tomorrow and they can bury the lines and start wiring everything up.  There are still a few rocks that will need to be moved to complete the wall after the trenches are filled, the pavers need to be repaired, and we're requesting that a rock is placed in the center planting bed and the first rock in the wall is moved so it's not touching the oak tree there.  Things should wrap up on Wednesday for the crew and there will be some quiet before the plaster guys come next week.  So much of our lawn irrigation has been destroyed, I'm scared to see how much the repair bill will be for that.  American Lawn Sprinkler is coming out next Monday to give a quote for that work.  Also, we'll need to get the pool fence installed some time soon after the pool is completed.  Lots of last items on the list before we can call this complete.


In the Trenches

   With the completion of the pool patio, the week ended with all the trenches dug and conduits and plumbing lines laid.  The electrical and gas to the equipment pad still needs to be laid, but that will be done next Monday, with Tuesday being slated for inspection  before the trenches can be filled back in.  It's a good time to take some pictures for posterity in case this area needs to be ripped up again for landscaping, or if service work needs to be done on any of the lines.

 

   Here's what the trenches look like from the pad.  The trench on the right is going towards the house and where the electrical and gas penetrations will be from the under deck storage.  Code states that they have to penetrate the house at a certain height above grade, so they'll be visible before they run down the wall  into the ground.  It's very minimal visibility.  The both of the conduits coming from the house are buried a bit deeper than required, at 24", which is good since we won't have to worry about hitting them when we come back in for landscaping in this area.  The main water supply pipe for irrigation was severed for the utility trench, but Tango Pools will reconnect it before the trench is filled.

   Here's the main trench for all the supply, returns, and lighting.  Although the lines towards the pool were buried before the patio started construction, some of the brick edge needed to be removed to gain access to the pipes to connect them to longer lines.  The gray vertical conduit sticking up near the patio will be for the pool side power plugs.  We'll use those for a robotic pool cleaner, or just plugging whatever we need at the side of the pool.

    Here's a look at the pool trench from the patio side.  You can see the edge of the patio that needed to be removed, and hopefully the repair will be just as strong as the initial installation.  The vertical conduit for the pool side electrical outlet is more visible, and will be cut down to code height.  It will probably be sitting in some plantings so it won't stick out like a sore thumb.
 
    Here's a closer look at the pipes in the trench.  The four gray conduit lines carry power for the 3 pool lights and lights for the bubbler.  On the water side, there are three  2" lines for the two skimmers and single bottom drain.  There are three 1.5" lines for the returns.  One is for the bubbler, and two for the four returns.  The pool has 4 return jets and they're grouped in two's; the grass side and the lake side.  Both of these lines will be connected to the pump outlet  on a single valve so all four jets should have fairly equal flow rates.  I've seen recommendations to have each return on it's own valve, but I've also seen plenty of installations without it.  If it's useful in the future, maybe I'll modify the pool to have a valve manifold, but the only advantage I can see is either for flow balancing or winterization.  The bubbler has it's own line since it will be on it's own power actuated valve.  We'll probably crack the valve open slightly for normal operation so the sun deck as some water flower for filtration purposes.  The Jandy app will allow control of the lights and the bubbler valve, which I can also integrate into our Control4 and Home Assistant systems.

   Here's were all the lines from the pool come down to.  The gray conduits are terminating where the primary panel will be.  Electrical from the house will come to this point and there will supply the panel.  There will also be an additional outlet here that I can plug the future landscape lighting panel into.  The water lines continue past and will hook up to the pump and filtration system.  
 
   Here are all the water lines, with a good shot of the equipment pad and all the equipment we'll be using.  I thought the pad was just going to be a simple concrete pad, but Tango Pools took it a step farther and used the same color stone to create a nice looking pad.  You can see they excavated down a few feet and compacted stone for the base.  There's probably some concrete inside the pad, but it's capped in stone.  The water flows in the supply side from the pool, into the pump, then through the canister filters, heater, salt water generator, water sanitizer, then out to the return (pressure) side.
 

   Here's the heater we're using.  It's a Jandy KXIQ400NK Versaflo 400K BTU.  The gas line will connect to that blue connector, and all the plumbing connections are on the other side.  I think the top can be removed and reversed, which would be nice since there's a control panel on the other side.  The main exhaust will be coming from that black box that says "HOT" and will just vent to the air.

   This is the "versaflow" part of the system.  It's valve that shunts the water from the input to output when there isn't a call for heat.  That saves on some wear to the heat exchanger, which is only made of copper.  I've read that as long as your pool chemistry is good, you don't have to worry about premature wear on a copper exchanger.  The top plug with the green line is also a sacrificial anode for the heater.  We'll also be installing a secondary sacrificial anode, so hopefully both of them will help extend the life of the equipment a little.  Pool heaters should last between 15 and 25 years with proper maintenance.


   Here are the boxes for the water sanitizer and salt water chlorinator.  I'm not sure where the sanitizer will sit in the flow, but the chlorinator should sit after the water heater I think.  The sanitizer is the Jandy TruGuard Mineral Sanitizer and the chlorinator is the AquaPure saltwater pool system.  I was unfamiliar with the mineral sanitizer, but it looks like it's just a cartridge system that leeches copper into the water to minimize algae growth.  It claims to reduce chlorine usage but I've read mixed reviews about it.  Some people say that the copper can build up in your water and cause staining.  You're supposed to replace the cartridges every 6 months, or once a season, so I'll have to keep an eye on it to determine if we want to use it in the system.

   Here's the canister filtration tank.  Initially, we were shipped the CL series filter, which has the input and output on the same side, but Eli exchanged it for the CV series, which has the ports on opposite sides.  It allows for better flow and easier integration into the system.  Inside are 4 filters that will require maintenance throughout the swimming season.  You just have to close the valves, loosen the retention ring around the middle and wash out the filters.  There's a bottom drain on the back side of the unit for winterization and flushing any sediment that gets trapped inside the tank.  I'm planning on getting extra filters so I can quick swap them and wash off the dirty ones so they're ready for next time.

  The pump we'll be using is a 2.7HP Epump from Jandy. It's a variable speed pump, so you can run it at lower speeds for longer times to reduce noise levels, but still get the calculated pool water turn over rate you desire.  All the Jandy equipment is controllable so not only will it be easy to turn lights and pumps on, I'll be able to program run times once I calculate actual flow rates after head losses so I can really dial in the filtration times.  I'm looking forward to figuring out all the controls and integrating it into our home automation systems.

   That's if for now.  Monday will see all the lines connected, ready for inspection.  We're expecting everything to wrap this week and final plaster either Monday or Tuesday next week.  I still have to get information about water for the initial fill, but hopefully we'll be swimming soon, if the weather holds out a little bit more.





Friday, September 6, 2024

Paver Patio: Part 2 Completed.

   Day two saw the completion of the paver patio.  I guess in real time, it was more like day four, but things have been moving so quickly, I haven't been able to keep up with the blog posts.  Still, four days to complete a whole paver patio is super fast and I'm really impressed with the quality of the installation.


    Here's a look at the entire pool area, which is in the end of the back yard.  I think a significant amount of soil will need to be brought in to level the yard to the new height of the pool patio and I'm not sure if it will be completed by Tango Pools, or if I'll need to find a way myself.  Fall is a great time to plant seeds since the cooler days make water requirements less important, so hopefully I'll get enough time to get everything amended and fixed up before snow starts to fall.  
 

   Polymeric sand has been swept into all the paver cracks and watered to lock them into place.  The larger gaps of the soldier course of stone are just filled with mortar, as is the edging where it meets the grass.  I've installed paver stones before on smaller projects and used a plastic edge with long nails to contain the edges.  Eventually it shifts and fails so hopefully this method will last longer.  Some of the sand will be raked away so I can get good soil up to the edge for grass, but I'm not sure how close to the patio the grass will be able to grow because of this mortar border.

   Here's a shot of the patio and sunshelf from the deep end of the pool.  I think the sunshelf will be a really great feature for just sitting on the edge and relaxing with your feet in the water.  We're going to try to get one if the extra wall boulders in the center planting bed as a nice landscaping feature, but I'm not sure if any of the rocks are small enough to fit, and still have room for a japanese maple.

    Here's a shot of the pool from the main part of the patio.  This area was supposed to be sunken for a fire pit sitting area, but later decided against it.  It will still make a really nice sitting area for lounging chairs.

   That's if for now.  Tomorrow, the slab will be constructed and trenches will be dug for all the water supply/returns and utilities.  Inspection for the electrical conduit is scheduled for next week Tuesday so everything should be wrapping up within the next week.  Hopefully we'll still have some warm days to enjoy the water.  I'll have to figure out who to go to for a winter pool cover and winterization.



Wednesday, September 4, 2024

Paver Install: Part 1

   Eli originally scheduled for the utilities and water lines to be trenched on the first day back after the labor day weekend, but instead had the crew start installing the paver patio stones.  The pavers have been onsite for a couple weeks now alongside the base sand pile and there's no reason why they couldn't start it.  Sprinkler lines and low voltage wiring have already been installed to the center planting bed and the bonding inspection has passed so everything that needs to be buried is already in the ground.  The paver install will be a pretty laborious project.  After leveling the base sand, the majority of the paver stones can be laid without much work, but all the edges will need to be cut to shape.  It's especially labor intensive on this pool since both the inside and outside edges of the patio are curved.  On top of that, the outside edge will have two curves; the curve made by the main stones, and the curve made by the soldier course.  Despite all the work involved, Eli is predicting the pavers will be completed by the end of the week.

   The majority of the work completed on the first day was in the deep end and front of the pool.  None of the outer edge was cut to shape, but some of the edges along the pool coping was fitted completely.  At this stage, it's possible to carefully step on the stones, but since they're not secured with the polymeric sand, you don't want to put too much lateral pressure and movement on the stones or they could slip.

   The crew roughed out nearly to the large sunning area of the deck and used a few of the pallets of pavers.  The edges of the center planting and grass will still need to be finished, but the majority is in place.  After having the back yard torn up for most of the summer, it's nice to have a finished surface to walk on.

   Some of the small pieces were cut up against the coping stones, which lend a glimpse into the final product.  The paver stones are flush with the top of the coping stones and should have a slight slope away from the pool so water drains to the grass, and not into the pool.  All that's left when the paver stones are completely laid is to sweep polymeric sand into the cracks, which will lock in the stones, and hopefully prevent weeds from growing in the cracks.  The stones are slightly dusty so the color is a little washed out and homogeneous.  You can see a little of the darker veining in the concrete stones, but it will mostly be a natural color pallet.  We've used concrete block coatings in the past on other projects.  It's basically an epoxy like coating that lends some protection to the blocks and darkens the color for a wet look.  I don't believe we'll be using that type of product on these pavers.  Concrete pavers are salt water resistant so I don't think we'll have to worry about durability with respect to our salt water pool system.

   One of the skimmer clean out boxes is in the paver section with the other being in the rear planting bed.  The pavers are nicely cut around the clean out box and sit flush with the top.  You can see that the bonding beam is covered with a layer of leveling sand.

This section of pavers is near the swim out steps and is nearly completed.  There will be a 3-4 foot paver path leading to these steps and will be bordered by the planting bed sandwiched between the pavers and the boulder wall.

   Here's that same section from a different angle.  You can see the smooth sand where the rest of the pavers will need to be installed.  The outside edge of this should be a nice smooth curve, bordered by the same brown soldier bricks.  We'll have landscape lighting in this bed which will also illuminate the paver walkway for any night time swims.

   I think the rest of the posts for this week will just be about the completion of the paver patio.  I'm a little in the dark about when the lines will be trenched, but it should be independent from the patio installation.  There's really not much left work to be completed before the final plastering of the pool, which is the last step before water delivery.  It's coming together quickly and we're almost going to be able to put this project behind us.


Tuesday, September 3, 2024

Retaining Wall Completed

   The boulder retaining wall was completed by the end of the week and all told took about a week to finish. It required an extra train of boulders to complete and we had to source the stones from farther up state since local reserves ran dry.  In all, the guys with Tango Pools did an excellent job fitting the stones together.  It was a task made more difficult since all the rocks needed to be brought up the driveway 2 at a time with the wheeled forklift, rather than having them dumped at the house.  The driveway wouldn't have been able to take the load of the boulder train.

   Here's a look at the top of the wall where the planting bed will be (left).  The lighter stone is the base rock of the paver patio.  You can see a faint paint line outlining the back edge of the paver patio.  A course of sand will be laid over the base stone and carefully leveled to proper drainage away from the pool.  After that, the patio pavers will be laid.

   Here's a wide shot at the pool area in totality.  The planting beds are pretty generous and will frame the back side of the yard nicely.  I'll have to call in irrigation to run new lines around the back of the pool, and repair any heads that were destroyed during the creation of the pool.

   This is where the boulder wall currently terminates near the end of the pool deck.  The paint lines in the dirt at the base of the wall estimate the location of the equipment pad.  The rest of the wall will be completed after the utility and water lines are run, to ensure that the wall won't interfere with the runs.  Eventually, the boulder wall will meld into a limestone wall, which will frame the stairs leading to the back yard, from the side yard.

   Here's the low sides of the boulder wall and the excellent work in fitting the stones together.  The wall ended up being almost 6 feet high in most places, which is why it required an extra order of stones.  The wall is backed with a geo fabric to retain the dirt and prevent animals from burrowing and undermining the retained soil.  I think it would be nice to put plantings in the crevices, if the wildlife allows it.

    Here's a wide angle shot of the boulder wall.  The land on the low side of the wall was used as access for machinery in the creation of the wall and is cleared of weed vegetation.  It's almost nice enough to use some how, but we're not sure if we'll purpose it.  A pool fence will be installed on the low side here, about 3-4 feet from the boulder wall so we might just end up planting it with wild flowers.

   The wall height near the deep end of the pool is only one boulder high.  The paver path around the deep end is only a three foot wide walkway, but there is a little space for some low plantings of we want some here.  The hope is that the 4 foot high pool fence will deter some of the deer from entering the back yard and allow us to actually have some plants.  I know deer can easily jump over the fence, but maybe it will make it just annoying enough for them to find easier pickings.  We've had limited success with hydrangeas, as they're routinely chewed down to the stubs.

   The pool equipment was also delivered at the end of the week, so we're all set for installation.  I didn't have time to take a close look at it yet, but I'll make a post about the equipment we're using with all the model numbers.

   That's it for this post.  Next up will either be paver laying or utility trenching/running.  The bonding inspection passed and the electrical and gas inspection will need to be passed before any equipment can be installed.   Things are definitely on the home stretch now that all the hard landscaping is completed.


Monday, August 26, 2024

Patio Prep: Course Stone

   Work continues to progress well with the installation and tamping of the coarse stone that will serve as a base to the patio pavers.  The crew was under a slight restriction today because the road coming to our house was going to be blocked for a few hours in the middle of the day.  A neighbor was getting his new pontoon boat lifted into the lake via crane since the lake association that controls the boat launch wouldn't allow him access.  Silly petty neighborhood politics.  Regardless of the limitations, Eli and his crew worked like crazy to get the rock and coarse sand dumped at the street, then shuttled to the back yard.

    The coarse stone provides a rough idea of where the pavers will be laid.  It overlaps the footprint of the actual pavers and will be covered by a fine compacted sand.  All this stone was dumped, spread, leveled, and compacted using a small plate compactor.

   The implementation of the swim-out steps changed a little from the initial design but the idea is the same.  A 3-4 foot wide paver path will circle around the deep end of the pool and meet up with the steps.  This new design removes a little of the planting bed on the back side of the pool, but not by much.
   Here's a shot of the paver base from the lounging side.  It's designed to be about 10 feet deep from the pool edge, which should give enough room for lounge chairs and walking space.  The back side of this area will have a planting bed as well.  The edge of the coarse stone is a little undefined, but the excavation machines still needed some access to the area from this point. 
   They started to clean out a path to the base of the boulder wall so they can construct it from below.  I'm hoping there won't be any long term negative effects on the oak trees they're winding through, as they can be a little sensitive to soil compaction.  I'll have to keep my eyes on them and give them extra fertilization if they start to look weak.  They survived the initial construction process and it would be a shame to lose them now.

   Boulders will hopefully be here Monday or Tuesday next week and they can start to construct the retaining wall.  Plumbing and utilities will need to be trenched before the wall is completed since the runs will go under the wall.  I'll need to put in some work and clear out the wood pile and raspberry bushes near the house penetrations for the utilities.  We're getting a last burst of summer with temperatures expected to be in the high 80's, so hopefully we'll get some warm weather in the fall to swim a bit.


Friday, August 23, 2024

Patio Prep

 Even with the delay on the boulders for the retaining wall, progress continues in other places.  Tango Pools came back to prep the front area of the pool for installation of the paver patio.  The prep will basically just involve digging down to a certain depth to introduce space for a base rock that will be compressed and provide a stable base for the pavers to sit on.  Before that can be completed, any thing that wants to run anywhere under the pavers need to be installed.  This includes irrigation lines for the planting beds, and low voltage wiring for landscape lighting.  I don't think all the pavers can be installed before the boulder wall is created since heavy machines need to get to the back side of the pool, but maybe the section of the patio near the deep end can be laid.
 
 

   Here's a shot of the excavation on the front of the pool, where the patio pavers will be laid.  There will be a large enough area for a round table and chairs, but there will also be a planting bed in the concave section of the pool.  They left a little pile of native soil where the planting bed will be, but we'll need to amend the very sandy soil with some good bed soil.

They installed two 1" irrigation pipes to the center planting bed.  I would imagine that one of them is slated to act as a conduit for electrical and the other is for actual irrigation.  There's a main trunk that runs somewhere in the area that the irrigation installers will be able to tap into.  As far as I can remember, there's one trunk for the rear yard lawn irrigation and one that runs the side of the yard for bed plantings.  There are still a few heads connected to the rear lawn irrigation that I would like to keep for just watering the grass.  There might need to be additional sprinkler heads installed to spray the grass away from the pool area.  Hopefully all the pool irrigation beds will be tapped into the side bed irrigation trunk.
   The excavator is sitting on the section of the pool patio that was originally slated to drop down in elevation for a little firepit sitting area.  We've since decided to no drop down in elevation, but will keep the same level as the rest of the patio, since it would have been more difficult to make a double bullnosed coping stone.  It would have been a nice feature but not a game breaker.  I think this area still needs to be excavated for the paver stones, and I'm also expecting irrigation and low voltage wires to run in this area.
   Here's another area where more excavation is needed for the paver install.  The swim out steps were shifted towards the skimmer in the original design, but needed to be moved towards the middle due to the location of trees.  Regardless, there's a paver path that wraps around this side of the pool to the swim out steps.  It will reduce the size of the planting bed on the back side of the pool, but that bed wasn't designed for any particular planting arrangement, just some low ground cover.

   Base rock is being delivered and spread tomorrow but I don't think it will look that different since the ground was pretty level to begin with.  Boulders will be delivered Monday and will be a bit of a circus, but progress is moving forward quickly.  I really have to hand it to the workers of Tango Pools.  They're here every morning at 7:30 and begin working at 8 and pull a full day.  I don't think we've had such great people installing at the house.