The thinner stainable beadboard was installed in the barrel vault. It seems like it makes the radius of the curve lesser, but it's probably because we're not seeing the internal structure anymore. It follows the curve of the front door so I know it's correct. The wood will be stained as close to the mahogany color of the door, Azek deck, and garage door as possible. Coordinating all four colors will be difficult but if they're pretty close in color, it will be good enough.
Here's an oddly blurry picture of the barrel vault; I'm not sure why this didn't come out better. The beadboard slats are red cedar, but will be stained darker to match the deck. I'm not sure how that will come out, but cedar is a good material to use outside. This is the same beadboard that will go up in the gazebo ceiling and will be stained the same dark brown mahogany color.
Installation and grouting of the exterior granite cobble stone is completed and the limestone ledge is in place. There are still some joints in the ledge stone that need to be filled, but it's pretty much done. There might be some grout filling down to the white drip edge, but I'm not sure if they'll do that after deck installation. Construction on the deck can now commence and some of it has been installed in other parts of the house. I'm not sure where the pressure treated wood stacked here is going since all the deck structure is completed.
Here's the front porch on the other side of the front door. It looks like all the ledge stone has been grouted, but there still might need to be some finishing at the bottom of the stone. Some of the smaller pieces are missing around the electrical receptacle so I guess that's proof that there's still some finishing work to do.
The entire side of the house looks the same as the front with regards to the exterior stone. The Azek deck boards will run perpendicular to the floor joists, so they'll run the length of the porch. They're twenty foot pieces, but the porch is much longer than that, so there will still be some butt joints down the course.
The lower porch pylons were completed and the exterior stone and limestone cap has been installed. Grout still needs to fill the gaps between the stones, and the farthest pylons still need some stone, but that will be completed quickly. After this is completed, the only remaining task is the application of the stone to the chimney.
As expected, the single piece, square, limestone caps were cut down the middle and a gap was created to allow the post to pass through. Also as expected, not all of the posts were perfectly centered in the middle of the pylon, and the wood boxing will have to conceal the variance between the posts.
Here's one that was off center from the pylons. You can sight down the pylons and see that they're all straight. Also, the posts are plumb and the beam they attach to is a steady eight feet from the house, so I'm not sure where we're getting out of parallel. This is the last post in the line and it's off by a half a thickness so the final box around the post will have to be at least two times the width of the post.
These are the last three pylons that need stone applied and I'm sure Old Country Stone will make short work of finishing them. It looks like OCS had to remove some of the finished stone on the wall where the last pylon sits. This last pylon will probably look integrated into the wall itself once completed. The lowest course of stone on these pylons will be below grade. You can see the limestone ledge on the basement sliding door, which will be partially covered by grade, and paver patio some time in the future. The ground will have to grade away from the house and there's a good foot or so that will need to be filled to accomplish this.
Moving inside, pieces of cedar bead board joins the every shifting stock of interior trim. Much of the window trim has been exhausted, and the remaining pieces are probably slated for door trim, once they're installed, and baseboard trim. Now that the interior doors are in the house, there will probably be a hiatus on the trim installation while the doors are set. After that, the door trim can be completed and the baseboard trim can go in since proper installation relies on a finished door trim.
A door and door frame sits at every door opening in the house. These two are sitting in the kitchen, but they're the two garage doors, one for the mudroom and one for the garage storage. These door frames are different in that they're the thickness of the ICF wall and they have weather striping to seal out the cold.
All the interior doors are solid wood, but the fire doors alone have these fire-rating tags on them. I'm not sure if they're made from a different wood or how they're constructed differently than the other interior doors, but these have a 20 minute fire rating. The holes for the door hardware were already drilled and the material looked like an LVL on all the doors, but knocking on the panels didn't yield any difference in the materials.
All the interior doors look the same, although they have some varying width. We tried to get all the doors at 34-36", but some are 32". All doors are eight feet tall with the only exception being the powder room door, whose height was limited by the rotunda structure. The increased height and weight of the solid doors necessitate four hinges rather than the standard three and all the hinges have ball bearings between the mating surfaces to make moving the door easy. The height of the door makes the width look narrow.
Here's a close up of the hinges. Square mortise brushed nickel finish with ball bearings on the resting surfaces. The door is on the left and the casing on the right with the ball bearings. The doors on our current house are hollow core with three brass curved mortise hinges. A black powder that looks like charcoal dust would build up around the hinges. This is because of the wearing of the metals grinding to powder and oxidizing. Even with frequent lubrication, we would get this black powder so ball bearings should prevent this, while allowing us to easily swing the heavy doors. The hinges are made by Penrod and having a square corner rather than a radius makes them a little harder to install. You can't use a round router bit to mortise the hinge plate, but you can use a router to remove most of the material and either a chisel or corner strike to cut the sharp corners.
The pantry doors are currently sitting in the pantry. When it comes to interior design, I'm generally hands off, relying on better minds than mine to make the aesthetic decision. This is one small part that I gave my input on since I see it as more of a functionality thing. The pantry is big enough for us, but it isn't a huge room and it sits near a traffic intersection. I though it would be a good idea to install a vertically split, spring hinge double door in the pantry for a few reasons. If your hands are full, you can just push open the doors for entry/egress. If we had a single door, it would either have to swing in, reducing the wall space for shelving, or swing out, blocking the traffic flow and pantry doors are rarely closed after use, so it would have been a hindrance. The narrow doors don't impinge upon the walking space much when pushed out, and occupy less space when pushed in. I really had to lay out my reasons and I hope this works out since it was all my idea.
The spring hinge mechanisms are cut into the bottom of each door, but otherwise, the door just has a pin on the top and bottom to swing on. A decorative metal plate covers the hinges and there's usually a "stay open" position you can push the door into if you really need it to stay out of the way. These doors have a slight radius eased into the edge so they clear the door jamb during operation. They have a similar arch top panel style, but are bisected by a vertical stile since there are two doors. I don't think they'll look out of place, and we might consider adding a metal plate for a pushing surface.
Wall tile in the mudroom bathroom has been installed, but none of the floor tile is in yet. This is going to be a more utilitarian bathroom, and we just happened to have enough room for a shower. It works out well because we can use it to wash a dog or people can use it to shower off after coming in from the future swiming pool. It's easy access from the back yard through the mudroom exterior door, and there's all tile surface in the mudroom so we don't have to worry as much about dirt and drips.
The mudroom bathroom vanity has also been assembled and set. Since we have an odd angled wall in this room, we got the vanity designed to fill the space with these shelves. It's probably a good place to store extra pool towels because anything else might not look good on an open shelf. The counter top will be a solid surface material and the sink will be a bit larger than standard undermount to provide a little extra utility.
The garage has finally been taped and mudded, but doesn't have any primer applied. The incorrect master balcony doors haven't been taken away yet but almost everything else has been removed from the garage. Garage doors are expected in the next few weeks, which should add some light to the space, but I'm not sure when paint will be completed. Eventually, we'll want to epoxy the floor since we've had great results with the DIY kit we applied in our current house. That might be after move in depending on the cost and how long it puts the garage out of commission.
This piece of curved railing is currently sitting in the greatroom. Besides the obvious curve, there's a slight curve in the vertical direction. I wasn't sure where it would fit at first, but after exploring the rest of the house, I'm pretty sure this is the stair railing for the first floor. The railing will begin at a newel post at the bottom of the stairs and end at another newel post at the top of the stairs so I don't think there will be a vertical transition to the rotunda railing.
The underside of the rail is on the left and the top is on the right. We went with a pretty standard and simple design, with a small bead running the length on both sides and a nice depression to grab onto. It looks like it's made of red oak and will be stained dark to match the floors. The floors are white oak smoked and stained dark, so the wood species is a pretty close match. I think the color staining will be close as well.
I almost missed the basement stairwell railing, sitting on the stairs, but there it is. We're only required to have one railing, by code and I think it's better to only have one. There's standard hardware available to attach railing to a wall, and I don't expect anything fancy will be used. I'll have to ask my aesthetically minded counterpart if she wants something cleaner looking than the standard.
The master bedroom eyebrow window trim is complete and ready for paint. The top curve window casing is just the kerf cut MDF without and veneer applied. I'm not sure if it's going to stay that way since it's just going to be painted, or if they'll apply a veneer to it now that it's in place. The latter would be a pretty difficult thing to do now that it's up and the MDF might provide a good enough surface once painted. Either way, I think they did a fantastic job with the trim and the shape really makes the room.
One finishing surprise is that the master bedroom dividing wall was clad in the "reclaimed wood" material. I think it's meant for floors and it's a luxury vinyl product meant to simulate real wood. It's about a quarter of an inch thick and has a very realistic texture, complete with radial saw marks. We chose this material because of the thickness and ease of installation. We needed something thick enough to miter on the corners to achieve the wrap around effect, which I think turned out well. The TV will be mounted on the bed side of the wall, but we don't have plans for the sitting area side of the wall just yet. I think it looks good and adds some character to the room considering it's a large dividing wall.
Another surprise is that Azek decking on the master bedroom balcony is completed. I knew deck installation was going to be starting up, but didn't expect this to be the first to be completed. Since the exterior doors aren't installed yet, we almost missed this addition, but we happened to be looking out the window and saw it. The temporary balcony door is held shut by four wood screws and since we didn't have a way to remove them, we just climbed out the window to check out the new decking. The balcony is eight feet deep and ten feet wide, so it will be big enough for a couple chaise loungers and a small table, which is plenty big enough for our use. We ended up lying around out here for a bit, just talking about life in general, something that we'll probably duplicate many times in the future.
Here's a look at the balcony as a whole. Some cedar shingle still needs to be installed on the angled dividing wall, both sides and we there will be a glass rail up here. The front of the balcony will have a standard installation, but the angled part will have a triangular shaped piece of glass to match the angle of the roof. I'm excited about having this extra sitting space off our bedroom. It provides good views of the lake, future pool if you're close to the rail, and gazebo if you're at the rail.
Prep of the master bathroom tile install comes in the form of the installation of our master vanity! These are Omega cabinets with a continuous grain walnut slab door with a floating vanity between two towers. The space under the vanity will be lit with low voltage lighting and the entire back splash will be tiled to the ceiling. Two Robern medicine cabinets will be installed in the spaces and we'll have three wall sconces for face lighting. The faucets are wall mounted and the sinks will be some kind of semi-basin design. This is way more storage than we have now, but we also don't have a small linen closet in this room, so I think many of the linens will be kept in the towers, along with toiletry resupply storage. I honestly don't know what I'll do with all the drawer space since I currently use the space under my sink and one drawer for all my stuff. Counter top items will be kept in the medicine cabinets, keeping the counter clean (ideally).
The drawers under the sink are "U" shaped to provide space for the drain plumbing. Since we have drawers in this cabinet, an under mount sink is not possible. I think this was a decision made way back when we ordered the cabinets, but honestly I can remember now. I don't think we have the sinks in this room nailed down yet, but I'm pretty sure we don't want a bowl shaped basin sink. Maybe something similar to what we're doing in the powder room with a semi-recessed basin if the drawer configuration allows for it.
The cement board in the master bathroom shower has been completed and coated in Redguard waterproofing. Apparently, cement board itself isn't completely water proof, as well as tile and grout, so an additional waterproofing membrane is needed, hence the Redguard. With this step, the bathroom is ready for tile.
Here's another look at the wet wall of the shower. The two large circular things at the bottom are mixing control valves. The left controls the shower and the right controls the hand shower and overhead shower. The and shower will be between the two mixers. You can see the master closet door past the shower entry on the left and master bathroom door through the shower entry on the right. We're not planning on installing any doors on either of these two shower entry ways but I have concerns that the shower will feel cold since all the heat and steam can escape into the bathroom. The door openings are 28", which sounds narrow, but our current shower has the same width opening, so maybe that's a standard measurement.
All the doors are present in this room, but need to be installed. As you can see, much of the baseboard has been installed, save for the areas near the door since they require a finished door trim to terminate into. We're planning on pulling out the base cabinets that flank the washer and dryer so that they'll be flush with the front of the machines. This will increase the depth of the countertop, but provide a more finished look to the space. The original plan was to have the machines sit proud of the side cabinets. Adding that depth shouldn't hinder access to the wall cabinets above them.
Distinctive Designs also finished the covering for the center style on the laundry room window. They created a box to cover the insulation and board that separates these two windows, and I think it came out rather nicely. Simple design, but adheres to the over all look of the rest of the window trim.
The turret bedroom is turning into the staging area for the rotunda woodworking finishes. It's currently holding the rotunda railing, all three newel posts, and the floor bullnose trim pieces for the rotunda floor. The rotunda railing is in three parts, but will probably be cut to fit the railing support posts other than the newel posts, if there are any. The three newel posts were boxed up for protection, but one of them was opened, giving me the opportunity to take a peek at it.
Like the railing, the newel posts are made of red oak, and have a paneled design like the first floor walls of the rotunda will. There's more detail and profile on these than there are in the rest of the house, but the style is similar to what will be on the front porch posts. They'll be cut to height during installation and the railing will attach to the flat surface near the top. These will also be stained to match the railing and floor color.
Here's a close up of the top of the newel post. It has a rounded off square cap that matches well with the level of detail in the rest of the house. A carved, figured top would have been out of place so something cleaner seems to fit well.
Here's a close up of the top part where the railing will attach to. There's no paneling detail on this section since you need a flat surface for the railing to attach. The section below it is paneled, supplying much of the fine detail to the post. The post is pretty heavy overall and very solid feeling. I haven't gotten a time line on the installation so when it goes up, it will be a nice surprise.
These pieces confused me at first, because I wasn't sure what function they served. After thinking about it for a bit, I realized that they're the bull nose trim that will run on the floor around the inner rotunda. The wood floor doesn't have a trim piece that can finish off the edge of the floor so Distinctive Designs is making these pieces so the floor has something to terminate against.
Here's one of the pieces in place. The underside is cut and the floating edge is rounded to provide a finished edge. I'm not sure if these pieces are just for testing or if they'll all be this short. Since the board itself is pretty wide, I'm guessing that they'll need to make these pieces short to accommodate for the curve of the rotunda. The trick will be matching the wood grain so it doesn't look segmented as it makes its way around the hall.
Two of the three round windows have been completely cased and trimmed ready for primer and paint. The large round window in the turret bedroom, at the center front of the house was unexpectedly larger, requiring the window trim to be cut down a bit to fit the closet wall, but that seems to be the worst of the fitment issues. The round casing turned out really well and makes the window really feel like a portal or ship port hole. The reveal of the window frame itself with respect to the casing is uniform which really adds to the quality of the install.
The wall tile in the turret bathroom has been completed and is awaiting grout and the shelf tiles. When the grout is applied to this wall, the tile in the turret bathroom will be near completion. Some of the bathrooms are getting a tile wainscoting, but I don't think this is one of those rooms. When the doors are installed and the door trim completed, this will nearly complete the room. Just counter, sink, toilet, and finished plumbing will be needed. We haven't decided what we'll do about the tub with respect to water control. We don't really like shower curtains, but it might be easier to use one while the kids are still young and we need to wash them. A sliding glass shower door is definitely better, but make the opening smaller. We'll probably end up using a shower curtain and later changing it to a glass shower door of some kind when the kids get older.
The compound windows on the first floor in the dining room and study also got the center divider covering, completing the trim out. We're still debating using window coverings on these windows since we're out in the middle of the woods, but even with the finished trim, we have plenty of sill space for blinds or curtains. I think we would like to keep them open since we like the depth; it makes a short bench to sit on. I'm thinking that nearly all the window trims are completed, just in time for the interior door and associated trim install. A couple of more weeks and the baseboard might be completed too, which would put us on track for painting at the end of June and wood floor after July 4th.
In the beginning of the final interior push, I found it hard to believe that it would take three more months to complete everything, but now I can see the amount of work left. Even with the work load, everything is progressing quickly with new and exciting developments every week. Next weekend, we'll probably see the installation of a few of the interior doors. I think paint colors are the next big decision to make with hardware second. As long as we have all the finish plumbing and electrical decision made, everything else is in the clear. 14 weeks left!
No comments:
Post a Comment