Thursday, August 22, 2024

Coping and Tile Completed. Lines Connected and Buried.

   The mortar for all the tile has been completed and the pool has received its first acid wash and will remain in this state until the very end when it gets plaster.  Meanwhile, all the drain and return lines were connected with flexible PVC pipes and buried close to the location of the pad.  Conduit was also connected to the stubs that run through the pool shell and run towards the pool pad direction.  Some ground work is needed to prep the area for the paver patio and boulder retaining wall, which should be happening soon.  A delivery of boulders was slated for the end of the week, but apparently boulders are in short demand in my area and need to be trucked in from another location, so that delivery was pushed until Monday next week.

   Here's a look at the deep end of the pool, with two drain lines and a gray conduit for the LED lighting.  The drain line coming in from the right is from the deep end skimmer and the other coming out of the ground is from the bottom drain.  Both run clockwise around the pool towards the shallow end and sunshelf since that's the direction of the pad.  They worked quickly to install these pipes and buried them so I had to take these pictures mid day.

 

    I believe these are the flexible PVC pipe being used for both drain lines.  The return lines are 1.5" diameter and the drain lines are 2" Spa-Flex rated at 60 PSI. I didn't get a close look at the return lines before they were buried but closer examination of the pictures I took show that the plumbing fittings for the returns are 1.5".

   Here's the deep end skimmer box with the plumbing run attached.  I've gone down the rabbit hole of difference between 90 degree sweeps vs. non-sweep and found mixed information.  Some people swear by the the sweeps since it allows for a reduced restriction for water flow.  Others say that 90 degree non-sweeps are fine.  This is a non-sweep fitting, but I'll try to make sure to get sweep fittings in the hard plumbing around the equipment.

   This is one of the returns near the sun shelf.  It doesn't circulate water on the shelf itself, but blows towards the steps.  The sunshelf has a bubbler that is used for water circulation.  If you look closely, you can see that this 90 degree fitting is labeled 1.5".  All the returns are marked on the coping stone, but it's a little confusing because the labels are reused between the two sides of the pool.  I would like each supply and drain line individually plumbed in the system with their own shutoff valves, so I'll have to make sure to tell Eli when the time comes.

   These 9 pallets of pavers showed up towards the end of the day and constitute the entirety of the patio.  The eight on the right are the primary stones and the one of the left is for the border.
The border stone label is shown in the picture.  Holland 4x8" in Elite Coffee color.  We chose to go with a darker brown since our rear garage door and all exterior doors are a similar color and will tie into the pool.

  These are the stones for the main field of the patio.  You can see the different sizes between the bottom and middle layer.  I think there's a pattern for laying these down, but the overall effect is that of no pattern.  They're large pavers and will hopefully stay level through all our seasons.

   This is the polymeric sweeping sand that will be used in the joints of the stone once it's all laid out.  The sand is very fine and has some binders in it that solidify when it's first watered.  It locks the pavers down and closes any cracks that plants could try to grow into.
   Here's a final shot of the pool from the shallow end at the end of the day.  All the pipes are buried and the ground around the pool is firm and level.  Eli said that the guys will be returning to start prepping the ground for paver work.  A certain depth needs to be established so that base rock can be leveled on which the pavers will rest.  I imagine this will also involve prepping the site for the boulder walls since they can't do any kind of final ground prep for the patio until the boulder walls are in since all the prep would get destroyed by the machines.  I'll also need to make sure that sprinkler line stubs to the back and middle planting areas, and low voltage wiring for lighting is installed before the final prep for the pavers is completed.  These things won't be hooked up right away, but need to be run to areas under the pavers.



Monday, August 19, 2024

Phase 2: Coping and Tile Installation Part 2

    Another day with perfect weather for working on the mortar joints and tile for the pool.  Progress is moving along quickly with all the coping stones seeing their joints recut and mortared.  The water line tile also saw prep work around the perimeter of the pool with some tile already being attached.  Eli estimates just one more day to finish off the water line and step border tiles, then it will be on to the retaining wall construction.

   The coping stones were all mortared down to the bonding beam and the gaps were recut to create even spacing.  The joints were then mortared to complete the coping stone surround.

   Here's a shot of the finished coping stones, before any water line tile prep was installed.  The top of the coping stones will set the level of everything else in the back yard; paver patio, retaining wall, and yard slope.

   They mortared the gap under the skimmer box to set the height according to the coping stone.  The paver patio will be laid on this big block of concrete surrounding the skimmer box, and will go right up to the skimmer box access port.

   A single ceramic tile was laid across the skimmer box opening in the pool to create a bridge for the coping stones.  The "nice" side of the tile is placed down and the coping stones are mortared to the bonding side of the tile.  Eventually, there will be a flapper door across the skimmer opening to help trap the floating debris.

   The electrician came and got a peek at the sub panel in the under-deck storage space that will be used to connect the pool equipment.  His main task for the day was to attach the copper bonding wire to the lengths of rebar that still remained long.  These rebar are electrically connected to the rest of the rebar cage so the entire pool is grounded together.

   A long length of copper wire was left, that will be tied to the rest of the electrical system to create a common ground.  This way, if there's any current leak from the lights in the pool, it will all ground out together.

   The prep for the water line tile involves driving in these wooden shims to establish level, and padding out the surface of the pool to bring up the depth of the thin waterline tile.  The tiles are only 1/4" thick so when combined with the surface prep and thinset, will bring the thickness up around 1/2", which is about the thickness of the rest of the surface plaster. 

   This update spans 2 days of work, before the rain came in for the weekend and ended the work day.  They did manage to squeeze in all the water line tile installation around the pool edge.  Additional furring strips were installed to create a ledge on which the tiles could sit.  On Monday, they'll return to grout the tile gaps and lay the small border tiles on all the horizontal edges around the pool.  This will be on the sunshelf and every step.

   Here's a shot of the pool at the end of the third day.  All coping has been set and grouted, and all tile has been set.  Work will resume the next week and should see the completion of the tile installation.


   The next steps will be a delicate balance of hard landscaping installation in the form of the boulder wall, and trenching for water returns and pool electrical.  Since the boulder trains can't make it up the driveway without destroying it, Eli says we'll need to lay sand down in the street and drop the rocks there.  They'll be shuttled up to the house by the wheeled Bobcat, then moved to the back yard with the tracked Bobcat.  I'm not sure if the mini excavator is up to the task of setting the stones, but we'll work in a counter clockwise direction towards where the pool pad will be installed.


Tuesday, August 13, 2024

Phase 2: Coping and tile installation part 1.

   Eli and Tango Pools have been finishing up other pool projects while our concrete shell has been curing.  I've diligently adhered to the concrete watering procedure and we're well past the safe period for curing.  Frequent rains have slowed the progress on completion of other pools since you can't plaster or mortar in the rain, but I've purchased a small pool cover pump to keep the water from building up in our pool and becoming a mosquito nursery.  The pump will be a good investment since we'll need one to keep the snow melt on the pool cover in check during the winter time.  With the other projects out of the way, now it's our time to push to completion.  Eli says we have about 4 weeks to completion, which will take us into the middle of September.  If the weather holds out, maybe we'll be able to take a few dips in to pool before we have to close it for the winter.

   A few pallets of coping stone were delivered to the back yard a couple of week back, but sat wrapped and remained uneventful.  The pool crew arrived yesterday with a tracked mini-dozer for the back yard, a wheeled mini-dozer for the front yard, a mini excavator, and a trailer full of various equipment.  These machines will live on the property for the duration of the build and will fill various roles to aid in completion of the project.  The wheeled mini-dozer will shuttle boulders up and down the driveway since we can't get the train of boulders to the house without tearing up all the asphalt.  The boulders for the retaining wall will need to be dumped in the street and carried to the back yard.  The tracked mini-dozer has been used to level the patio space around the pool and backfill the pool shell.  The mini-excavator will be used to set the boulder wall and trench for plumbing and utilities.

   All these actions will be taken in the future and now it's time for setting the coping stones and waterline tile.

   All the concrete forms were removed and some of the bonding beam rebar was cut to a short stub to later be connected to the grounding loop.  The stone were broken out of the pallet and laid on the bonding beam to set the spacing and ensure enough stones were purchased.


The on concave sections, the pool edge of the coping stones were set tight.  The stones will be cut with a gas powered stone cutting saw so that an even mortar joint can be achieved between the stones.

Here's a convex section of the pool, where the stone will be cut with more material being removed from the back.  Pool shell penetrations for lights and water returns were marked with purple paint since the pool shell was mostly backfilled to make it easier to work around.  These sections will be excavated later to connect plumbing and electrical runs.


There will be around a half inch of plaster installed on the concrete pool shell so the lip of the coping stone will only have around a 3/4 inch overlap.  The coping stones will be mortared to the bonding beam of the concrete shell and set level.  The top of the coping stone was the important measured elevation reference that referenced off the house.  It took into account a gentle slope away from the house to allow for water drainage, and also sets the height of the surrounding patio.  The patio will slope down away from the coping stone elevation.          

Most, but not all, of the bonding rebar was cut to a stub.  Recall that these are conductively connected to the rebar in the pool, and will all be wired together to ground before backfill and patio stone installation.


   The forms were also removed from the concrete fill around the skimmer boxes.  The top of the coping stones sit above the level of the concrete box so the pavers will be installed and cut around the skimmer box opening.

   Here's a shot from the deep end of the pool.  You can see that there's still some of the bonding beam available after the coping stone is installed.  This will provide a nice lip for the pavers to sit on and provide a flush surface since they're nearly the same thickness.

   Updates should be coming more quickly since the work should progress nicely.  I'm expecting most if not all of the coping stone to be set on the second day of work, but haven't seen any deliveries of water line tile yet.  Once those two items are installed, I think trenching for plumbing and utilities should be next since all that needs to be installed under the paver stones.  The water return lines will even need to be installed before the boulder wall since the equipment pad will be on the lower elevation of the wall.  After the plumbing runs are installed, I think the boulder wall will be constructed and the ground will need to be prepped and leveled for the paver stone installations, after which will be the final planting bed grading.  When all the dirty work is completed, the plaster and equipment will be installed.


Pool Surfaces and Materials

   Just a little update on the materials we'll be using in and around the pool.  We've landed on a more natural color scheme for the coping stone and patio pavers as shown in the picture below.  The pavers are Oaks Nueva in Champagne color.  I'm not sure who makes the small brown bricks, but they'll be used as a border brick on the edges of the patio.  The coping stone is on the right and pretty closely matches the patio pavers.  The water line tiles are a slate or bluestone gray and that small disk is a sample of the PebbleTec Tahoe blue.

 


 

Wednesday, June 5, 2024

Gunite Shooting Part 2 (Done)

   Despite the random power outage, the gunite crew finished shooting the pool today, complete with sun shelf, stairs, and swim out stairs.  All the equipment is gone from the property, but there remains a sand pile next to the driveway and some additional material in the back yard.  To prevent the gunite from curing too quickly, instructions are to water the pool three times a day for three days, then 2 times a day, then 1 time a day for no more than 10 days.  Online instructions say to water it for at least 2 weeks and you can't over water it, so depending on the weather, I'll probably keep hitting it for 2 weeks.  I think we're going to be waiting at least 3-4 weeks for the pool to harden before we see any more progress so updates will slow down a bit.

   Here's a look at the finished gunite shell from the deep end.  The bottom of the walls are slightly curved into the bottom.  There's a nice bevel that leads into the skimmer boxes, which sit flush with the top of the concrete.  The top of the wall has a fairly crisp corner on which the coping stone will sit.  You can see the difference in color between what was shot the first day and what was completed on the second, but I think that's more from the moisture content.  I don't believe the watered the first day shooting today so I lightly watered it.
   Here's what the finished sun shelf looks like.  As indicated by the initial design, there are three steps up and a fourth for the sun shelf.  Keep in mind that there's still a coping stone that will sit up on the edge of the pool, and you don't want the step out of the sun shelf to be too great.  The depth of the water will be about half way up the skimmer box, which makes it around 4-6 inches deep on the shelf.  I think it's enough to sit with or without furniture in that area.  I think the two lower pipes in the wall are for LED lights and the middle, higher one is for the water return, but I'll have to look back in pictures to confirm as any markings on the pipes have been obscured.

   Another shot of the sun shelf and steps.  The bottom step feels a little bit higher than the top two, but I think it's intentional.  I think the steps will have the Pebbletech plaster applied to the top, with edging and faces getting tile.  I think the greater height of the lowest step, which is a very minor difference, will be made up with the plaster coat on the bottom of the pool.  Each wall penetration is beveled around the pipe, probably to either allow for more plaster around the fittings, or to allow for clearance for the fittings themselves.  All of this will be smoothed out by the plaster coat.  The sun shelf will be a really nice place to sit and relax if you don't want to go fully in the pool.

   Here's a look at the swim out stairs.  The water level will be about half way up on the wall above the top step so both steps will be submerged.  This will allow someone to swim and easily sit on the bottom step, then hang out, or get out without having to climb a ladder.  I think a secondary egress point is required in a pool design and this satisfies the need very well.  It's not specifically in the deepest part of the pool, but it's pretty close and off to the side of the longest swim path in the pool.  Great place to take a rest while swimming laps for exercise.  The bottom step doesn't quite completely fill out the convex curve of the pool, but it's really close.

   Here's what the swim out steps look like from above.  I believe these steps will also get a tile border, and you can see why that's important.  From above, and especially when these steps will be submerged, the two steps would blend together without a tile border.  The step sits between the two skimmer boxes, so I'm hoping that any floating debris will be picked up by one of those two instead of whirlpooling in this area.  The pool deck here will only be a 4 foot path with planting beds to the boulder retaining wall.  That path won't connect to the main pool deck area going counter clockwise around the pool so you'll have to walk clockwise around the pool to get to the main deck.  I'm hoping that won't be too much of an annoyance and I guess if you really want to, you can walk on the pool coping stone.

   The skimmer boxes are completely embedded in concrete and mostly covered.  There's a square top and lid that will sit on this and interface with the surrounding patio pavers so all the concrete here will be hidden under the pool decking.  There was some short pieces of rebar sitting in the area that I believe were installed when they shot the gunite around the skimmer box, but I didn't get to see the process.  I'm not sure if there's a standard or optimal angle for the gunite around the skimmer opening but as far as I understand it, the skimmer simply makes a low pressure suction to pull in debris that's floating by the orifice.  We do have oak trees around the pool and in the fall, they drop acorns, which I don't believe float, so we'll need to clear out the bottom of the pool.  I don't think the main drain can fit an acorn, nor do I think I would want to keep emptying the pump basket to remove them.  The pump basket will need to be emptied once or twice a week anyways so it looks like a weekend/Wednesday type of situation for cleaning out skimmer and pump baskets.

   Last picture is a pool side shot of the skimmer opening.  I've read that optimal water level is 1/3 to half way up the opening and with the coping stone that sits on top, the water level will probably be around 5 or 6 inches from the top of the coping stone.  Normally, the plaster layer is around 1/2 inch thick and it looks like the gunite leaves just about that much space to the actual skimmer orifice so water should flow smoothly.  The coping stones are about 8 inches wide, so I'm guessing there's a longer coping stone that can bridge the gap across the skimmer opening because it would seem dangerous to have a seam in the stone over an unsupported space.

   That's it for today.  I think I'll be able to put together a post about pool finishing materials while the pool shell hardens, but I'll otherwise be out of topics to discuss until the finishing time comes.


Tuesday, June 4, 2024

Gunite Shooting Part 1

   Wasting no time, Joe and his crew came today for the first of two or three gunite shoots for the pool shell.  Late last week, they dropped off equipment and left a few trucks in prep for the shoot this week.  We had the skid-steer, gunite mixer/shooter, and some kind of generator or air compressor sitting on the pullout of the driveway over the weekend.  The skid-steer moved the machines to the back yard to be closer to the pool site.

   Here's the shooting in operation.  The machine in the middle would take bags of concrete in one hopper and the skid-steer would race to the front yard where they dumped the sand and bring up a bucket to dump it into the main hopper.  The corkscrew lift would mix the two and water connected via hose would add moisture.  The mix would dump into another hopper at the end of the lift and from there it would run out the large diameter hose to be shot at the pool.  The bags of concrete on the left are labeled "Saint Mary's Cement Type IL Portland limestone cement".  The internet says that IL Portland cement uses more limestone content than normal Portland cement.  The bags on the larger stake are labeled "Onecem type IL Portland Cement" so they're both IL cement, which is supposed to have a lower carbon footprint than normal Portland Cement.  I'm sure there are other cement-based science differences for IL Portland cement, but it's probably not relevant to this pool.

   Here's another look at the equipment used for gunite shooting.  You can see the large Doosan 750 portable air compressor in the background near the house.  It has a large hose that connects to the gunite mixer, but I think it's just for the actual shooting of the material.  The gunite mixer itself has a gas powered engine to power the mixer and lift.

   Here's a shot of the pool from the deep end at the end of day 1.  The gunite was shot up most of the side of the pool, with the remaining portion to be completed the following day.  That second day shoot will require a little more accuracy since it will entrap all the stubs and skimmer boxes.  The left side of the pool saw some erosion behind the metal so they slipped a piece of the plywood behind the metal to reduce the amount of extra gunite needed to fill the void.  Since there's a water return penetration at the space, it will eventually be excavated for plumbing access and backfilled, so I'm not worried about the ground integrity when it's all done.  Also, this curve will feature a small planting bed so the soil will need to be amended anyways.

   Here's a shot of the deep end with the Eclipse pool drain installed.  There are disposable caps on the round and center section which are used to block material and protect the drain.  These caps will stay in place until pool start up.  As predicted, the whole drain pipe channel was shot with gunite, encasing the pool drain pipe.  The gunite was troweled for shape but it's not a super smooth surface, which will come later from the plaster finish.

   The skimmer box areas saw forms placed around the whole assembly, using the wood structure installed by Eli as a guide.  It looks like the entire skimmer box will be encased in gunite, but the finished paver surface will sit on top of this concrete block.  The preinstalled drain pipe from the skimmer still exist the rear of the box form and is currently buried. 
   Some excess gunite was shot in the swim out step area, but the steps themselves haven't been formed yet.  The underlying shell needs a little bit of hardening before those are shot and formed.  I spoke briefly with Joe before they started work in the morning.  He requested the color plans so he could use them as reference, and said that the shoot will pretty much adhere to the plans.  The plans call for two steps, and while there's no code for riser height, he said he likes to make them about 8-10 inches in height, so there will be two swim out steps.

   Just like the swim out steps, the sun shelf hasn't been shot yet.  The bubbler remains uninstalled, but it looks like they left a notch in the gunite they did shoot to allow for pipe passage.  The plans call for three steps coming off the sun shelf, with the sun shelf itself being about 8 inches deep.  Joe said that the depth of the sun shelf will be dependent upon the coping stone because you don't want to have a really high step coming out of the pool.  Typically, sun shelfs are 8-10 inches deep and loungers that sit in sun shelfs can be 2.5 inches thick, leaving 6 inches of your siting area in water with your legs and most of your torso out of the water.  So three steps plus the sun shelf at 8 inches per step puts us at 40 inches, which is 3 feet 4 inches for the beginning of the shallow end of the pool.


   One of the skimmer boxes was installed at height and the other remains to be installed.  You can see how they cut the rebar around the box, and this one still needs the rest of the box forms installed.  The stub pipes were placed a bit below the water level and were cut through the form to be jammed into the dirt.  Eli said the gunite shoot should be take a few days to complete and afterwards, we would need to water the pool every day to control the speed of drying.  Online instructions state that the gunite should be watered at least 3 times a day for at least 14 days, especially if the weather gets hot.  The gunite should absorb much of the water sprayed on it and help with the curing.  Since concrete curing is exothermic, spraying water keeps it cool and prevents cracking.  I might need to get a sprinkler on a timer to handle the mid-day watering since I can't work from home every day for the next few weeks.

   Here's the thickness of the pool being shot.  It looks like the metal structure sits a couple inches below the gunite shell and there will be another half inch of plaster on top of that.  When I was leaving for work in the morning today, the crew was already on site prepping for shooting so I'll get to see how much progress they'll make today.  It's a little more precise for the rest of the pool and there's still some prep to be completed for the skimmer and bubbler, but if they move as fast as they did yesterday, it almost seems like they could complete it on the second day.

  Unfortunately, the driveway took some damage from all the heavy machinery.  It was a little expected and in general pool installation circles, there's not much that can be done about it.  It generally falls under the home owners responsibility to repair so I'll have to cut this part out and patch it, either during the 28 days it takes for the gunite to cure, or after everything is completed.  Pool deck installation will require more heavy materials to be moved and probably some machinery, especially for the boulder wall installation so I might just let this sit until the fall after everything is installed and the weather is cooler again.  Remember, the driveway was never really finished with a final top coat because we knew we would have heavy machinery driving back there for the pool and all the other remaining landscaping installations.  Even after the pool area is completed, we'll still need some retaining wall and steps installed leading to the back yard, two paver patios for each basement walkout, and a deck that goes around the garage.  I'll patch this area so it doesn't crumble more, but when everything is finally done, we'll probably get the driveway resurfaced and completed.

   That's it for this update, but I'm certain there will be another coming soon that will show the completion or near completion of the pool shell.  Afterwards, there will probably be a lull while the shell hardens, but it will pick up again for the final plumbing and finishing of the pool.


Monday, June 3, 2024

Plumbing Placement

   Eli showed up today to lay out plumbing locations for the main drain, return, bubbler, and sub locations for the LED lights.  The main drain was located in place and a length of rigid PVC was connected since it would be entrapped by the concrete when it's shot for the pool shell.  The returns and LED lights were marked on the pool forms and just consist of enclosed pipes filled with gravel for weight.  They'll be jammed into the sand at their designated locations to provide pass through for their respective functions.  Since the bubbler will be in the sunshelf, it's just laid near the location of installation.  The skimmer boxes were again marked on the wood forms as well as placed at the desired locations, while having their orifices blocked to prevent ingress of concrete during the pour.

   Here's a picture of the deep end of the pool.  The long PVC pipes leaning up on the wood forms are the stubs for returns and LED lights.  The trench on the right side of the picture is the main drain line coming up from the deep end.  You can also see the skimmer box on the right side of the picture.  The PVC with the 45 degree pipe isn't marked for anything, so I believe it's extra.

   Here's where the main drain pipe comes up from the main drain.  The pipe stub comes up to the ground level, but I'm not sure if it will ultimately stay that depth (height?) or if it will be cut off at a lower depth before the pipe run is attached and run to the pump manifold intake.

   Here's the main drain in place with the drain pipe attached.  There's a 45 degree fitting that looks to sit in the concrete shell which I hope won't cause any issues to the strength in that location.  When the pool is completed, there will be a surface matched cover that covers the drain.  You can see that the pipe being used for a pass through stub is labeled "LED lights"  It doesn't mark at what depth the lights will be placed at, so I'm guessing there's a standard depth for such things.  After the pool shell is shot, the ground where these stubs are will need to be excavated to access the dirt side for whatever they're passing through.  They're probably just sleeves for the lights, but I'm not sure if the returns will use the actual PVC as a connection, or if the PVC stub is oversided to allow passage of the actual return pipe.

Some additional wood was installed around the skimmer box locations.  The top and the pool opening have been closed off to prevent concrete incursion, but a single 2 inch drain pipe has been attached.  There's an additional cover that goes on the top of the skimmer box, which will sit at the level of the pool deck so height placement is very important for this item.  The skimmer boxes also determine the height of the water in the pool since you don't want the water level too high above the opening.  Generally the pool water level should be about half way up the skimmer box opening, so getting this placement needs to take the final height of the coping stone into account.  Probably the most important detail of the initial pour process.

   Here's a look at the plumbing coming off the skimmer box.  Both skimmer boxes will be placed on the lake side of the pool and the return jets will circulate the water clockwise to promote flow into the boxes.  We have a lot of trees around the yard, so hopefully this will help keep the pool free of leaves.

   Here's the placement location of the second skimmer box.  Both skimmers are in concave parts of the pool to help with the trapping of surface objects.  I think the wood forms will need to be cut away here before the concrete is shot, but that will be done by the gunite crew.  Again, additional wood supports were installed in this location and I believe it to just be supports, not forms for the skimmer box.  The skimmer box will mostly be immobilized in the pool shell and I don't think they'll use any concrete on the outside of the shell to lock in the rest of the box, but I'm not sure about that.
   Here's a shot from the shallow end, showing the path of the main drain plumbing and the two skimmer box locations.  The PVC pipes placed on the rebar are for the returns, 4 in total.
   At first I was a little confused about the height the main drain plumbing takes to get out the pool.  When the gunite is shot, that whole channel will be filled in, so it looks like the drain pipe will level off at the or near the height of the water.  I thought you would want the pipe at a deeper depth so the pump wouldn't experience any head loss on the drain side.  After reading a bit online about plumbing design, it looks like you don't want the main drain suction dictated by the depth of the pool.  By raising the drain line up to near the water level of the pool, you're making sure that only the pump is dictating the suction strength at the drain, and water pressure or siphon.

   Here's the bubbler plumbing.  There are two PVC lines connected to the bubbler.  The larger 2 inch line is the water return and the smaller gray conduit is for electrical lines since the bubbler also contains an LED light.  Eli mentioned that there are a few different openings for the bubbler that dictate the height of the water fountain.  He also said that the bubbler will be able to flow water out the sides a bit to keep the sun shelf water circulating and clear of debris.

   Here's a last look of the pool with the PVC stubs and metal in place before they come and shoot the gunite.  I think the gunite shoot is a 2 step process; 1 shoot for the rough shell and a second shoot for the final shape and sun shelf/swim steps install.  The shell needs to be hardened a bit for the later two items, but I don't know the timing of the two shoots.  After that will be the long wait while the shell cures strong enough for final surface treatments.